On 17 November a developer said it had begun construction on a 22.5 MW DC floating solar complex sitting on a flooded mine pit at an active crushed stone operation in upstate New York. Germany's largest floating array is on a flooded lignite pit as well. Quarry and mine pit lakes may be the most overlooked water class in US floating solar — and the one where the engineering diverges most from a retention pond.
What was announced in New York
According to Third Pillar Power's announcement carried by CleanTechnica on 17 November 2026, the company is building Crown City Solar, a three-phase, 22.5 MW DC complex — 7.5 MW DC per phase — on an approximately 120-acre flooded mine pit at the Polkville Crushed Stone Facility in Cortlandville, New York, a site operated by Suit-Kote Corporation. D3Energy is the EPC. Phase 1 is expected to reach commercial operation in February 2027 and phases 2 and 3 in October 2027, serving roughly 1,500 community solar subscribers. The company says it reached construction less than two years after securing site control and applying for interconnection.
Treat the superlatives in that release as the company's own. The number worth stealing is the schedule: under two years from site control to construction at that scale. That is a site-control story more than a permitting story — one industrial owner, one parcel, one queue position, and a water body with no recreational users to object.
Why a pit lake is attractive, and what you have to check
| Working in your favor | What it forces you to verify |
|---|---|
| One commercial owner; no HOA board, no residential shoreline | Is mining still active in that pit, and for how long? |
| Already-disturbed industrial land; little land-use conflict | Reclamation plan on file and the approved post-mining land use |
| Three-phase service, substations and haul roads often already on site | Available capacity at the existing service, not just its presence |
| Large, often deep water with no recreational use | Water depth and bank slope — these drive the mooring design |
| Water level frequently managed by pumping | Who controls the level, and the full range in writing |
The infrastructure point is the one that moves a pro forma. A Nature Conservancy roadmap written with Downstream Strategies and the WVU College of Law found up to 400,000 acres of former mine lands and other brownfields in central Appalachia that could meet minimum suitability requirements for large-scale solar, and argued the appeal is "existing infrastructure, such as transmission lines, substations and access roads" (TNC roadmap, PDF). The same logic scales down to a 200 kW behind-the-meter array: a crusher is typically a large three-phase load, with a service sized for it.
Depth and water level are the design drivers
A retention pond is shallow and flat-bottomed, so bottom-set deadweight anchors are usually the cheapest answer. A quarry pit is neither — benches are often steep and the bottom tends to be rock rather than silt. Bottom anchoring in that geometry means longer chains, more ballast and more barge time, which is why pit-lake projects tend to pull anchoring to the bank or to fixed piles.
Germany's largest floating plant shows the pattern at scale. On the Cottbuser Ostsee — the former Cottbus-Nord open pit mine, flooded since 2019 — LEAG and developer EP New Energies built a 29 MW plant across 16 hectares with some 51,000 modules, anchored on "dolphins," 15-meter tubes set into the lake. The array was assembled on the dry lake bed and floated up as the water rose. The stated reason for that approach was low-maintenance anchoring: fewer anchors, and no long run of anchor chains needing readjustment as the level rises and falls (Bayern Innovativ / Energie & Management, 17 May 2023). That same article cites Fraunhofer potential of up to 2,700 MW on mining lakes in former German coalfields.
Water level is the sharper risk on an operating site. In a stormwater pond the level moves with rainfall; in a dewatered pit it moves because someone turned a pump on. Mooring has to accommodate the operator's full managed range, including the drawdown they intend during the next phase of extraction, and the slack has to be designed in from the start. Our components page covers what is in a structure kit and what is not; the mooring and anchoring design is site-specific engineering either way.
Water chemistry, and the coverage question nobody has answered
The best field data on deep man-made pits comes from the Netherlands. Deltares monitored Dutch deep sand-extraction lakes at Oudehaske (roughly 15% and 36% covered) and Beilen (roughly 45%): light at 1 m depth was lower under the arrays at every reading, with a maximum average reduction of 41%; median dissolved oxygen at 1 m was 8.9 mg/L under the array against 9.55 mg/L in open water, with a January 2023 minimum of 4.27 mg/L versus 6.49 mg/L; chlorophyll-a was higher in open water on nearly all dates (Deltares report, PDF).
Those effects cut both ways — less algae, but less oxygen near the surface in winter. US field work points the same direction: in a four-pond study published in Frontiers in Water, coverage ranging from 4.8% to 71% produced lower chlorophyll-a at one site, higher at another and no discernible trend at two, and the authors concluded effects were site-specific and that coverage alone did not predict the outcome (Cagle et al. 2025). If a pit discharges to a receiving water under a state permit, expect the regulator to ask — and expect the answer to be a baseline monitoring plan rather than a citation.
The permit stack is a mining permit stack
This is where quarry projects differ most from the retention pond work most installers start with. Mined land is already permitted land, and the operative document is the reclamation plan and its approved post-mining land use. Adding a generating asset to a pit lake can mean amending that plan. States have been clearing the path unevenly: Nevada's State Environmental Commission voted in June 2018 to add renewable energy to the list of permissible post-mining uses alongside grazing, agriculture, recreation, industry and wildlife habitat (Nevada Independent). Florida wrote mine pits directly into statute: s. 163.32051, F.S. defines a floating solar facility to include one sited on "abandoned limerock mine areas" and makes it a permitted use in the appropriate land use categories of every local comprehensive plan (statute text).
What those provisions do is zoning and land use. They waive nothing else. Local building and electrical permits and the utility interconnection process apply to a pit lake exactly as they do to a farm pond, and federal jurisdiction over the water body is site- and state-specific — many private isolated waters may be non-jurisdictional after Sackett, but that is a determination, not an assumption. Our permitting overview sets out the framing we use.
What the structure costs, and what moves the rest
Structure-kit pricing from our published Gen3 catalogue, structure only — panels, inverters and wiring are separate:
| Kit | Panels | DC watts | Kit price | $/W |
|---|---|---|---|---|
| 20 kW three-phase | 32 × 640W | 20,480 | $4,796 | $0.234 |
| 20 kW single-phase | 36 × 560W | 20,160 | $5,680 | $0.282 |
| 10 kW single-phase | 18 × 560W | 10,080 | $3,633 | $0.360 |
The volatile line is modules, not floats. Section 232 minimum import prices take effect at 12:01 a.m. ET on 4 December 2026, at $0.22/W for cells and $0.38/W for modules, plus 15% ad valorem on derivatives (EY tax alert). Anza reported a median imported module price of 27¢/W before the proclamation among suppliers that later repriced, against 38¢/W for delivery after 4 December (Anza). On the tax side, the 48E credit does not apply to solar placed in service after 31 December 2027 unless construction began on or before 4 July 2026 (Olson Partners).
Before you quote a pit lake, collect these five things:
- A bathymetric survey, or at minimum soundings along the intended array footprint and the nearest bank.
- The managed water-level range for the next ten years, from whoever controls the pumps, in writing.
- The mining permit and reclamation plan, with the approved post-mining land use highlighted.
- Twelve months of interval data from the site's existing service, plus the service capacity.
- Any discharge permit for the pit, and the baseline water-quality data it already requires.
Run production and payback through the ROI calculator once you have the interval data, and see how the system goes together for the mechanical basics. Dealers and EPCs quoting this site type can reach us directly.
Bottom line
A flooded quarry gives you what a residential pond usually cannot: a single industrial owner, heavy three-phase service already on site, and water with no competing recreational use. It takes back the easy part of the engineering — the shallow, flat bottom you can deadweight-anchor cheaply — and it adds a reclamation plan to the permit stack. The projects getting built are the ones where somebody surveyed the depth and pinned down the water-level range before anyone priced a kit.
This is general information, not tax or legal advice. Permitting and tax treatment depend on your site, your state and your facts — confirm both with your own counsel and tax advisor.
Sources: CleanTechnica · Bayern Innovativ · TNC mine-lands roadmap · Deltares · Cagle et al. 2025 · Nevada Independent · s. 163.32051, F.S. · EY · Anza · Olson Partners